When we decided to move forward with building a new home we decided to go the prefabrication road and chose Quality Engineered Home as the provider. After a lot of thinking, many questions and meeting with Quality Homes representative Julie Armitage, we have reached the magic moment when our house flies home to its final perch. This was the first time we saw the outcome of our decisions and choices made late fall of last year. In one day, our home now sits at about 80 percent complete. Now it will take about six weeks to fully finish and we can begin to move in.
So you can have a sense of how events unfolded during the week I have summarized each day beginning with financing just in time through to the last day of the week when the hard working crew had a weekend to refresh themselves to continue the following week. That is one thing I can not say enough, these people from Quality Homes are beyond professional, they are focused, precise and personable to no end.
Day One – May 31, 2021
We generally live in a trailer for six months out of the year in our “Condo on Wheels,” now you might say this week will result in a step up or, more accurately, a quantum leap in our living accommodation for the other six months of the year. To finance this type of build we secured a Construction Mortgage which allows you to draw funds as required to keep your build moving forward towards completion. For a modular home, in our case, this draw of funds is the final cost of the home upon delivery. They will not ship the modules without a guaranty you have the funds in hand to give to the driver when they arrive because of the logistical nightmare involved to move oversized loads down Ontario highways. Permits, equipment, manpower, and various utilities staff required to move low-hanging wires are all need to be coordinated to move prefabricated modular homes.
Well, despite negotiating with the bank nearly eight to ten months in advance of the delivery date and arranging a lawyer to register the mortgage with time to spare, it was down to the wire to get the funds before the arrival of our home. The bank was ready to give out monies but the lawyer was not so accommodating despite communicating with them three months in advance, so we were running around the day of the delievery. With a gentle pushed from Quality Homes explaining the extent of the affects of not having the funds available in time and the efforts of our mortgage broker to ensure the lawyer was able to receive the funds in a timely manor, we were able to provide the funds in time.
Day Two – June 01, 2021
An early start to the day, grabbing chairs, water, the dogs and umbrella for some shade, we were off to the building site to watch the two halves of our home be placed on the foundation. What a show it was for us and a small handful of interested neighbours.
First on site was the crew, a well oiled machine if I have ever seen one. Everyone had a task and a place to be throughout the next four hours required to place each half on the foundation. We were the next on site setting up our viewing position followed shortly after by the in-laws. Following this was the 300 tonne crane, a massive beast and well overkill for the task at hand. The smaller, more appropriate crane was not available today I was told. Now was the beginning of the setup period to lift the building. For a massive machine this crane is surprisingly agile.
Next was the parade, two halves of our building moving effortlessly towards their final resting place, our foundation. The crews began preparing the first half for the lift, unpacking the building from its road dressings and preparing to place the straps and lifting harnesses. This was our first time to have an unobstructed view of the interior. Next they positioned the module in front of the crane. In the meantime, a second crew was completing the final tasks before the lift, like removing the roof structure of the garage they had just built, while waiting for the crane to set up. Once clear of that the first half was airborne. About 20 minutes later, it was in its final position after and few minor adjustments. They took the time to reposition this half by a quarter of an inch. This screams professionalism let alone precision. Now time for the second half, much the same process and procession. Next the roof peaks, ridge beam and then on to the garage. Four lifts later, a garage for two. There was even roofing shingles started on the roof structure as the crew not required for the lift were working on other tasks such as the garage roof shingles.
With the heavy lifting done, the crane was packed up and sent on its way. We were approached and invited to see our home for the first time once they had made it safe for us to do so. This was the first time the lines on the drawing, which we spent hours pouring over; adjusting this or that, moving a wall here and there, requesting a light here and not there, became real. What a feeling it was knowing there was a final product on the horizon.

Day Three – June 02, 2021
It was down to a crew of two to keep moving our project forward as the balance of the crew from the day before, were off to the next lift on Manitoulin Island. They worked on closing up the building sealing the two halves together. We did not get over to the site until later in the afternoon to see them pouring the concrete porch at the front door. They also had the back of the building completed with vinyl siding. I am sure there was a longer list of tasks completed but those were the two most visible during a drive by. We do not want to get in the way of their progress as they have instructions to put down their tools if we or another visitors are onsite.

Day Four – June 03, 2021
Much of the same as above continued on this day, more buttoning it up, or closing up the exterior to make the building water-tight. This included completing the roof singles, placing a roof over the porch and more siding. It is looking great from the street now.

What is Up for Next Week
We have been told the basement floor will be poured next week along with the sewer and water hook-ups. Then in the weeks to follow the other utilities will be added but more on that in the next instalment.